Hillwood Construction Services, Inc., a Texas Corporation

Administrative - Formal · FY2002 · — · Unilateral Administrative Order Without Adjudication · 85114

Penalty
Cost recovery
Compliance action

Case

Case Number
06-2002-1867
Type
Administrative - Formal
Lead
EPA
Outcome
Unilateral Administrative Order Without Adjudication
Multimedia
Self-disclosure
N

Defendants (1)

Summary

'Violation: 1) Storm Water Pollution Prevention Plan (SWPPP). **Relief: 1) Within thirty days, Respondent shall take action to correct violations; 2) Within thirty days submit written report detailing specific actions taken to correct violations; and 3) If correction of violations is not possible within thirty days, submit comprehensive plan to do so.'