# Sorrells Development Corporation and H & B Contractors
> **Administrative - Formal** · FY2002 · — · Final Order With Penalty
## Case
- **Activity ID:** `85159`
- **Case Number:** 06-2002-1874
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- H & B Contractors (complaint) (settlement)
- Sorrells Development Corporation (complaint) (settlement)
## Summary

**VIOLATIONS: 1) Inspections were not documentted in the SWPPP from May 2001 to October 1, 2001; 2) Portions of silt fencing were either installed incorrectly or very poorly  maintained; and 3) Certification statement for the SWPPP was not signed by the authorized corporate officer of the company.                                                                     **PROPOSED PENALTY: $27,500.00.

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*