# NORTH BRONSON FORMER FACILITES OU3 ADMIN ORDER ON CONSENT (CERCLA)
> **Administrative - Formal** · FY2002 · — · —
## Case
- **Activity ID:** `85772`
- **Case Number:** 05-2002-0329
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** —
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- SCOTT FETZER (complaint) (settlement)
## Summary

'PRP will conduct RI/FS at Operable Unit #3 of the site.  OU#3 consists the former Scott Fetzer manufacturing plant in Bronson, Michigan.  OU#3 was used for the metal plating operations.  The plant used the industrial sewer to dispose their industrial waste to the lagoons of the North Bronson Industrial Area (NBIA) Superfund Site .  The NBIA Superfund Site consists of 2 set of lagoons (eastern and western lagoons) and County Drain # 30, and located at northern of the OU#3..'

---