# PUERTO RICO ELECTRIC POWER AUTHORITY - CAMBALACHE
> **Administrative - Formal** · FY2002 · — · Unilateral Administrative Order Without Adjudication
## Case
- **Activity ID:** `8740`
- **Case Number:** 02-2002-1002
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unilateral Administrative Order Without Adjudication
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** N
## Defendants
- PREPA - CAMBALACHE (settlement)
## Summary

THIS ORDER IS BEING SENT TO PREPA CAMABALCHE TO ORDER   THEM TO REMOVE THE SCR SYSTEM FROM THE 3 SIMPLE-CYCLE OIL    FIRED GAS TURNBINE LOCATED AT THE CAMABALCHE FACILITY.  THE  RESPONDENT WILL THEN RETEST THE UNITS (WITH STEAM INJECTION  ONLY) TO ESTABLISH THE CORRECT EMISSION LIMITS FOR NOX, PM,  PM10, AND H2S04, AND SUBMIT ANOTHER BACT ANALYSIS.           *

---