← EPA enforcement cases

USARMY - FORT DIX

Administrative - Formal · FY2002 · — · Final Order With Penalty · 8754

Penalty
Cost recovery
Compliance action

Case

Case Number
02-2002-1276
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

FORT DIX FAILED TO KEEP A LOG OF INSPECTION OF LEAKS AND A LOG OF THE TEMPERATURE READINGS FOR THE REFRIGERATED CONDENSER, AS REQUIRED BY 40 CFR SECTIONS 63.322(1) AND 63.323(A)(1). FORT DIX FAILED TO MEASURE THE TEMPERATURE OF THE AIR-PER GAS-VAPOR STREAM ON THE OUTLET SIDE OF THE REFRIGERATED CONDENSER ON A DRY-TO-DRY MACHINE WITH A TEMPERATURE SENSOR ON A BYWEEKLY BASIS TO DETERMINE IF IT IS EQUAL OR LESS THAN 45F. FORT DIX HAD PARAMETER VALUES MONITORED FOR THE REFRIGERATED CONDENSER WHICH DO NOT MEET THE VALUES SPECIFIED IN SECTION 63.232(A)(1) AND SECTION 53.323 (A)(2), THEREFORE ADJUSTMENTS OR REPAIRS SHALL BE MADE TO THE DRY CLEANING SYSTEM OR CONTROL DEVICE TO MEET THOSE VALUES. IF REPAIR PARTS MUST BE ORDERED, EITHER A WRITTEN OR VERBAL ORDER FOR SUCH PARTS SHALL BE INITIATED WITHIN 2 WORKING DAYS OF DETECTING SUCH A PARAMETER VALUE. SUCH REPAIRS SHALL BE INSTALLED WITHIN 5 WORKING DAYS AFTER RECEIPT AS REQUIRED BY 40 CFR SECTION 63.322(N).

Source

Authoritative
EPA ECHO
Machine
JSON-LD · Markdown