# U.S. v. Washington DOT and Southgate Development Company
> **Judicial** · FY2003 · — · Final Order With Specified Cost Recovery
## Case
- **Activity ID:** `88669`
- **Case Number:** 10-2003-0008
- **Type:** Judicial
- **Lead:** EPA
- **Outcome:** Final Order With Specified Cost Recovery
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- Southgate Development Company (complaint) (settlement)
- State of Washingto, Department of Transportation (complaint)
## Summary

Cost Recovery action to recover $11,165,948 in past costs for preliminary assesment, site investigation, and removal activities from October 1993 to November 2002 at the Palermo Willfield NPL site in Tumwater, WA.  Groundwater at the site is contaminated with TCE and PCE.

---