# GENERAL ELECTRIC CO-HOUSATONIC RIVER SITE
> **Administrative - Formal** · FY1998 · — · Unilateral Administrative Order Without Adjudication
## Case
- **Activity ID:** `928`
- **Case Number:** 01-1998-0121
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unilateral Administrative Order Without Adjudication
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** $12.50M
- **Multimedia (multi-env):** N
## Defendants
- GENERAL ELECTRIC CO (complaint) (settlement)
## Summary

EPA ISSUED A CERCLA 106A UNILATERAL ADMINISTRATIVE ORDER  TO GENERAL ELECTRIC COMPANY. THE UAO REQUIRED GE TO IMPLE-   MENT INTERIM MEASURES,SUBMIT A DATA REPORT, PERFORM SOURCE   CONTROL AND PERFORM CLEAN-UP MEASURES FOR THE TWO MILES OF   THE HOUSATONIC RIVER IN PITTSFIELD, MA.

---