# Fitch Petroleum Company
> **Administrative - Formal** · FY2003 · — · Final Order With Penalty
## Case
- **Activity ID:** `93782`
- **Case Number:** 06-2003-4312
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Final Order With Penalty
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- Fitch Petroleum Company (complaint) (settlement)
## Summary

1.  No Spill Prevention Control and Countermeasure Plan.
2.  written procedures and a raecord of inspections are nto maintained for three years.
3.  Secondary containment apperas to be grossly inadequate for tanks and central treating installations.
4.  Visual tank inspections are not conducted periodically by appropriate personnel and/or inspections do not include tank foundation and supports.

5.  Inadequate or no flowline maintenance program (inlcudes: examination, corrosion protection, flowline repalcement).

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*