# North Jersey District Water Supply Commission
> **Administrative - Formal** · FY2003 · — · Unilateral Administrative Order Without Adjudication
## Case
- **Activity ID:** `96174`
- **Case Number:** 02-2003-8091
- **Type:** Administrative - Formal
- **Lead:** EPA
- **Outcome:** Unilateral Administrative Order Without Adjudication
- **Penalty assessed:** —
- **Cost recovery:** —
- **Compliance action $:** —
- **Multimedia (multi-env):** —
## Defendants
- North Jersey District Water Supply Commission (settlement)
## Summary

Failure to certify that a vulnerability assessment was performed and send a copy of the assessment to EPA Administrator.  Cost to perform/evaluate/prepare/send assessment to EPA Administrator is @ $20,000.00 (based on population, system size and nature of technology required, etc.).

---
*Source: [EPA ECHO](https://echo.epa.gov/) · AI Analytics · CC0 1.0*