UPPER MORELAND-HATBORO JOINT SEWER AUTH.

Judicial · FY1985 · — · Final Order With Penalty · 9829

$10K
Penalty
Cost recovery
Compliance action

Case

Case Number
03-1985-0029
Type
Judicial
Lead
EPA
Outcome
Final Order With Penalty
DOJ Docket
90-5-1-1-2484
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

THE AUTHORITY OWNS & OPERATES A 6.6 MGD SECONDARY SEWAGE TREATMENT PLANT LOCATED IN WILLOW GROVE, MONTGOMERY COUNTY, PA. THE AUTHORITY IS AUTHORIZED UNDER NPDES PERMIT # PA0025976 TO DISCHARGE WASTEWATER FROM THE PLANT INTO THE PENNYPACK CREEK. THE AUTHORITY HAS FAILED TO COMPLY W/THE PRETREATMENT PROGRAM REQUIREMENTS OF ITS NPDES PERMIT. EPA IS SEEKING INJUNCTIVE RELIEF & A CIVIL PENALTY IN THE AMOUNT OF $25,240.