7/3/03 - COMPLIANCE ORDER ISSUED. PURSUANT TO THE GENERAL PERMIT PROVISIONS, ITEM 12, COMPLIANCE CERTIFICATIONS, OF THE REPONDENT'S PERMITS, RESPONDENT WAS REQUIRED TO SUBMIT COMPLIANCE CERTIFICATIONS TO THE REGIONAL ADMINISTRATOR OF EPA REGION 4 AS SCHEDULED:
DEAMANVILLE: FOR THE YEAR STARTING MARCH 10, 2002 THRU MARCH 10, 2003 BY MAY 9, 2003;
REFORM COMPRESSOR STATION: FOR THE YEAR STARTING MARCH 10, 2002 THRU MARCH 10, 2003 BY MAY 9, 2003;
SELMA COMPRESSOR STATION: FOR THE YEAR STARTING MARCH 10, 2002 THRU MARCH 10, 2003 BY MAY 9, 2003;
ELMORE COMPRESSOR STATION: FOR THE YEAR STARTING DECEMBER 28, 2001 THRU DECEMBER 28, 2002 BY FEBRUARY 26, 2003;
YORK COMPRESSOR STATION: FOR THE YEAR STARTING DECEMBER 29, 2001 THRU DECEMBER 28, 2002 BY FEBRUARY 26, 2003;
AUBURN COMPRESSOR STATION: FOR THE YEAR STARTING DECEMBER 28, 2001 THRU DECEMBER 28, 2002 BY FEBRUARY 26, 2003.
ACCORDING TO EPA RECORDS FOR COMPLIANCE CERTIFICATIONS AS OF JUNE 26, 2003, RESPONDENT HAD NOT SUBMITTED COMPLIANCE CERTIFICATIONS TO THE REGIONAL ADMINISTRATOR OF EPA REGION IV