# Air Plan Approval; Georgia; 2015 8-Hour Ozone Nonattainment New Source Review Permit Program Requirements
> **Rule** · Final rule. · Published 2022-01-25 · Effective 2022-02-24 · 87 FR 3677
## Document
- **Document number:** 2022-01299
- **Category:** air-emissions
- **Federal Register citation:** 87 FR 3677
- **CFR reference:** 40 CFR 52
- **Publication date:** 2022-01-25
- **Effective date:** 2022-02-24
- **State:** GA
- **EPA docket:** EPA-R04-OAR-2020-0406
## Abstract

The Environmental Protection Agency (EPA) is approving a revision to the Georgia State Implementation Plan (SIP) submitted by the State of Georgia through the Georgia Environmental Protection Division (GA EPD) on July 2, 2020. EPA is approving Georgia's certification that its existing Nonattainment New Source Review (NNSR) permitting regulations meet the nonattainment planning requirements for the 2015 8-hour ozone National Ambient Air Quality Standards (NAAQS) for the Atlanta Area, comprised of the counties of Bartow, Clayton, Cobb, DeKalb, Fulton, Gwinnett, and Henry. This action is being taken pursuant to the Clean Air Act (CAA or Act) and its implementing regulations.

## Source
- [Federal Register document](https://www.federalregister.gov/documents/2022/01/25/2022-01299/air-plan-approval-georgia-2015-8-hour-ozone-nonattainment-new-source-review-permit-program)
---