**Report:** Audit of the U.S. Army Corps of Engineers Use of Undefinitized Contract Actions for the Conversion of Alternate Care Sites in Response to the Coronavirus Disease–2019 Pandemic ([detail](https://api.ai-analytics.org/ig-report/28397))
**OIG report number:** DODIG-2021-074
**Recommendation number:** D-2021-0074-D000AV-0
## Text
Rec. 1.c: The DoD OIG recommended that the U.S. Army Corps of Engineers Director of Contracting issue a memorandum directing contracting offers to differentiate the profit associated with undefinitized contract actions dependent on the contractor's decreased cost risks involved in completing work in an undefinitized status, and the incentive to definitize contracts based on Defense Federal Acquisition Regulation Supplement guidance.
---