# Audit of the U.S. Army Corps of Engineers Use of Undefinitized Contract Actions for the Conversion of Alternate Care Sites in Response to the Coronavirus Disease–2019 Pandemic
> **Audit** by Department of War OIG · 2021-04-07
> *About: Department of War*
## Report
- **Title:** Audit of the U.S. Army Corps of Engineers Use of Undefinitized Contract Actions for the Conversion of Alternate Care Sites in Response to the Coronavirus Disease–2019 Pandemic
- **Submitting OIG:** Department of War OIG
- **Component agency:** Department of War
- **Type:** Audit
- **Publication date:** 2021-04-07

## Recommendations

- **Rec D-2021-0074-D000AV-0** (Closed): Rec. 1.c: The DoD OIG recommended that the U.S. Army Corps of Engineers Director of Contracting issue a memorandum directing contracting offers to differentiate the profit associated with undefinitized contract actions dependent on the contractor…
- **Rec D-2021-0074-D000AV-0** (Closed): Rec. 1.a: The DoD OIG recommended that the U.S. Army Corps of Engineers Director of Contracting complete an after-action review following the completion of the coronavirus disease-2019 mission to identify best practices and areas of improvement when…
- **Rec D-2021-0074-D000AV-0** (Closed): Rec. 1.b: The DoD OIG recommended that the U.S. Army Corps of Engineers Director of Contracting issue guidance requiring contracting officers to document the reason definitization schedules were not met in the contracting files.
## Source
- [oversight.gov report page](https://www.oversight.gov/reports/audit/audit-us-army-corps-engineers-use-undefinitized-contract-actions-conversion-alternate)
---