A methane ignition occurred on the 17-w section #3 entry at 6:15 am on 5/8/10. The section was placed on a J order and then modified to a K order to allow temporary roof supports to be installed so packers could be installed on both sides of the vertical-horizontal de-gas holes (well BH-3A st 2).