At 2:28am, power went out. Upon investigating the surface transformer they noticed the center phase had blown. Realizing power was not going to be restored, MSHA was called, and an evacuation was initiated. Further diagnostics determined it was an internal fault on the transformer that had been in service for 34 days. Transformer was removed from service and spare was installed.