Spool Piece was to be installed on pump. It was rigged with a sling and a shackle, going around the pipe once. The Spool Piece was lifted into place, the flanges were an 18"" on one end and a 10"" flange on the other, the weight shifted on the load pinning one of the crew members right hand between the sling and the 10"" flange.