The miner completed bolting a partial slab round in the -515 EMLD heading. The ground support was installed as per the GCMP. The miner and the shift supervisor were standing approximately 10' behind the bolter when fine material was observed trickling out of the supported area. Fractured rock material then fell from the area and came to rest against the right side of the bolter.