# MSHA citation `8534227`
> **Significant & Substantial** · Citation · 02/05/2018 · Zhengzhou Coal Mining Machinery Group Co., Ltd.
## Rule
- **Section of Act:** —
- **Part / Section:** 48.7(c)
- **Type:** Citation
## Severity
- **S&S flag:** Y
- **Likelihood:** Occurred
- **Injury/Illness:** Fatal
- **# affected:** 1
- **Negligence:** HighNegligence
## Money
- **Proposed penalty:** $4,717
- **Amount paid:** $4,717
- **Amount due:** $4,717
- **Contested:** N
## Parties
- **Mine:** [0100851](https://api.ai-analytics.org/mine/0100851) — Oak Grove Mine
- **Violator:** Zhengzhou Coal Mining Machinery Group Co., Ltd. (Contractor)
- **Controller:** —
---