# NRC ORDER – NOV (White)
> **EA-08-124** · ORDER · Issued 2008-08-01 · Reactor Licensees
## Action
- **EA Number:** EA-08-124
- **Licensee:** NOV (White)
- **Category:** Reactor Licensees
- **Action type:** ORDER
- **Date issued:** 2008-08-01
## Description

On August 1, 2008, a Notice of Violation was issued for a violation associated with a White Significance Determination Finding to Nebraska Public Power District involving a violation of Technical Specifications which requires that written procedures be established, implemented, and maintained. Specifically, an inadequate work order instruction and maintenance procedure resulted in a loose electrical connection on an emergency diesel generator and the subsequent failure of the diesel generator.

## Source
- [Full enforcement letter (PDF)](https://www.nrc.gov/docs/ML0821/ML082140518.pdf)
- [NRC Reactor Licensees index](https://www.nrc.gov/reading-rm/doc-collections/enforcement/actions/reactors/)
---