# Streamlining Electric Program Procedures
> **Rural Utilities Service** · Final rule; change of effective date. · Published 2019-07-12 · Effective 2019-07-09 · 84 FR 33163
## Document
- **Document number:** 2019-14875
- **Category:** rural-development
- **Sub-agency:** Rural Utilities Service
- **Federal Register citation:** 84 FR 33163
- **CFR reference:** 7 CFR 1710
- **Publication date:** 2019-07-12
- **Effective date:** 2019-07-09
## Abstract

On July 9, 2019, the Rural Utilities Service (RUS), a Rural Development agency of the United States Department of Agriculture (USDA), published a final rule that revised several regulations to streamline its procedures for Electric Program borrowers. RUS has determined it is necessary to accelerate the effective date of the final rule.

## Source
- [Federal Register document](https://www.federalregister.gov/documents/2019/07/12/2019-14875/streamlining-electric-program-procedures)
---