Building for the Future Through Electric Regional Transmission Planning and Cost Allocation
other · US Department of Energy · Published 2024-12-06 · Effective 2025-01-06 · 89 FR 97174
Document
Document number
2024-27982
Federal Register citation
89 FR 97174
CFR reference
18 CFR 35
Type
Rule
Action
Order on rehearing and clarification.
Category
other
Sub-agency
US Department of Energy
Publication date
2024-12-06
Effective date
2025-01-06
Energy docket
Docket No. RM21-17-001
Abstract
In this order, the Federal Energy Regulatory Commission addresses arguments raised on rehearing, sets aside, in part, and clarifies Order No. 1920, which required transmission providers to conduct Long-Term Regional Transmission Planning to ensure the identification, evaluation, and selection, as well as the allocation of the costs, of more efficient or cost-effective regional transmission solutions to address Long-Term Transmission Needs. Order No. 1920 also directed other reforms to improve coordination of regional transmission planning and generator interconnection processes, require consideration of certain alternative transmission technologies in regional transmission planning processes, and improve transparency of local transmission planning processes and coordination between regional and local transmission planning processes.