Modification of Interchange and Transmission Loading Relief Reliability Standards; and Electric Reliability Organization Interpretation of Specific Requirements of Four Reliability Standards
electric-grid · Federal Energy Regulatory Commission · Published 2008-07-28 · Effective 2008-08-27 · 73 FR 43613
Document
Document number
E8-17196
Federal Register citation
73 FR 43613
CFR reference
18 CFR 40
Type
Rule
Action
Final rule.
Category
electric-grid
Sub-agency
Federal Energy Regulatory Commission
Publication date
2008-07-28
Effective date
2008-08-27
Energy docket
Docket No. RM08-7-000
Abstract
Pursuant to section 215 of the Federal Power Act, the Federal Energy Regulatory Commission (Commission) approves five of six modified Reliability Standards submitted to the Commission for approval by the North American Electric Reliability Corporation (NERC). The Commission directs NERC to submit a filing that provides an explanation regarding one aspect of the sixth modified Reliability Standard submitted by NERC. The Commission also approves NERC's proposed interpretations of five specific requirements of Commission-approved Reliability Standards.