RESPONDENT COMMENCED CONSTRUCTION OF BOILER NO. 5 ON OR ABOUT APRIL 2, 1988, AND BEGAN OPERATING THE BOILER ON OR ABOUT FEBRUARY 1, 1989. BASED ON INFORMATION SUBMITTED BY GOODYEAR SULFUR DIOXIDE EMISSIONS FROM THE BOILER TRIGGERED PREVENTION OF SIGNIFICANT DETERIORATION REVIEW.