← EPA enforcement cases

FITCHBURG WWTF

Administrative - Formal · FY2011 · — · Final Order No Penalty · 2600024760

Penalty
Cost recovery
Compliance action

Case

Case Number
01-2011-2043
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order No Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

Administrative Compliance Order requires the City to complete construction of interim phosphorus upgrades to its WWTF by November 30, 2012, and to achieve compliance with a 12-month rolling average interim total phosphorus limit of 0.5 milligrams/liter (“mg/l”) no later than March 31, 2013. The Order also includes a schedule for completion of construction of a more extensive upgrade of the WWTF by May 31, 2019 and achievement of compliance with the 0.2 mg/l monthly average total phosphorus limit contained in its 2010 Permit by November 30, 2019. The Order further requires the City to design and construct priority sewer separation work in Project Areas CSS 3 and CSS 4. The scopes of these projects are delineated in attachments to the Order

Source

Authoritative
EPA ECHO
Machine