← EPA enforcement cases

C.D. MOODY CONSTRUCTION COMPANY, INC.

Administrative - Formal · FY2012 · — · Final Order With Penalty · 2600075713

Penalty
Cost recovery
Compliance action

Case

Case Number
04-2012-1502
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

11/17/2011 - CONSENT AGREEMENT AND FINAL ORDER ISSUED, ASSESSING A PENALTY OF $6,373. RESPONDENT SHALL MAKE PAYMENT WITHIN THIRTY DAYS. ORDER ALLEGES: DEMOLITION OCCURRED BETWEEN MAY 5, 2011, AND MAY 8, 2011, AT A FACILITY FORMERLY LOCATED AT 400 0AK STREET SOUTHWEST IN EASTMAN, GEORGIA (THE FACILITY). THE FACILITY BEING DEMOLISHED WAS A SINGLE COMMERCIAL BUILDING THAT HAD BEEN USED AS A MCDONALD'S RESTAURANT. RESPONDENT OWNED, LEASED, OPERATED, CONTROLLED OR SUPERVISED THE DEMOLITION OPERATION AT THE FACILITY. RESPONDENT IS THEREFORE AN OWNER OR OPERATOR OF A RENOVATION OR DEMOLITION ACTIVITY. RESPONDENT VIOLATED SECTION 112 OF THE CAA, 42 U.S.C. SECTION 7412, AND 40 CFR SECTION 61.145(b) BY FAILING TO PROVIDE THE STATE OF GEORGIA WITH WRITTEN NOTICE OF INTENTION TO DEMOLISH THE FACILITY.

Source

Authoritative
EPA ECHO