← EPA enforcement cases

Camden County Public Works

Administrative - Formal · FY2015 · — · Final Order With Penalty · 3600181409

Penalty
Cost recovery
Compliance action

Case

Case Number
02-2015-7921
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
Self-disclosure
N

Defendants (1)

Summary

An EPA Contractor performed an inspection on January 22, 2014 and found a failure to perform annual line tightness test or perform monthly monitoring on pressurized piping, failure to conduct line tightness testing or use monthly monitoring on suction piping, and a failure to provide adequate line leak detection system for underground piping.

Source

Authoritative
EPA ECHO
Machine