← EPA enforcement cases

Essex Water District et al.

Administrative - Formal · FY2020 · — · Unilateral Administrative Order Without Adjudication · 3602135857

Penalty
Cost recovery
Compliance action

Case

Case Number
02-2020-8009
Type
Administrative - Formal
Lead
EPA
Outcome
Unilateral Administrative Order Without Adjudication
Multimedia
Self-disclosure
N

Defendants (3)

Summary

System must construct water treatment plant for compliance with Stage 2 DBPR according to revised compliance schedule.

Source

Authoritative
EPA ECHO
Machine