← EPA enforcement cases

SPRING VALLEY CONSTRUCTION, CONTROL SPECIALIST, INC., SITE C

Administrative - Formal · FY2002 · — · Unilateral Administrative Order Without Adjudication · 41978

Penalty
Cost recovery
Compliance action

Case

Case Number
06-2002-1809
Type
Administrative - Formal
Lead
EPA
Outcome
Unilateral Administrative Order Without Adjudication
Multimedia
N
Self-disclosure
N

Defendants (9)

Summary

1. SECTIONS 308(A) AND 309(A) OF THE CLEAN WATER ACT ( CWA ) 33 U.S.C. SECTIONS 1318(A) AND 1319(A). 2. SPRING VALLEY CONSTRUCTION, A TEXAS CORPORATION CONTROL SPECIALIST, INC., A TEXAS CORPORATION SITE CONCRETE, INC., A TEXAS CORPORATION GLENN THURMAN, INC., A TEXAS CORPORATION MORRISON HOMES OF TEXAS, INC., A TEXAS CORPORATION MHI PARTNERSHIP LTD., A TEXAS CORPORATION HIGHLAND HOMES, LTD., A TEXAS CORPORATION NATGUN CORPORATION, A MASSACHUETTS CORPORATION PHOENIX FABRICATORS, AN INDIANA CORPORATION FACILITY: RAYZOR RANCH DEVELOPMENT LANTANA TRAIL AND RAYZOR ROAD DOUBLE OAK, DENTON COUNTY, TEXAS 75067 3. RESPONDENTS WERE IN VIOLATION OF SECTIONS 301 AND 402 OF THE CWA BY EACH DAY THAT RESPONDENTS CONDUCTED THE RELE- VANT ACTIVITES AND OPERATED THE FACILITY WITHOUT NPDES PERMIT COVERAGE AND BY VIOLATING THE TERMS AND CONDITIONS OF ITS PERMIT. 4. RELIEF SOUGHT PURSUANT TO SECTIONS 308(A) AND 309(A) OF THE CWA, EPA ISSUED AN ADMINSTRATIVE ORDER (AO) THAT ORDERED THE RESPONDENTS TO: A) WITHIN 30 DAYS, OBTAIN NPDES PERMIT COVERAGE, SUBMITTING A COPY OF THE APPLICA- TION, CONFIRMATION OF COVERAGE AND THE PERMIT NUMBER TO EPA; B) WITHIN 30 DAYS, TAKE CORR

Source

Authoritative
EPA ECHO
Machine