Administrative - Formal · FY2001 · — · Final Order With Penalty · 53766

$250
Penalty
Cost recovery
Compliance action

Case

Case Number
09-2001-0059
Type
Administrative - Formal
Lead
EPA
Outcome
Final Order With Penalty
Multimedia
N
Self-disclosure
N

Defendants (1)

Summary

THIS IS A AN UST COMPLAINT CONSENT AGREEMENT/FINAL ORDER (CA /FO). A CA/FO WAS ISSUED FOR THE FOLLOWING VIOLATIONS:FAILU RE TO PROVIDE ANY CORROSION PROTECTION FOR METAL PIPING; FAI LURE TO USE AN OVERFILL PREVENTION SYSTEM; FAILURE TO PROVID E ADEQUATE RELEASE DETECTION METHOD FOR PETROLEUM TANKS; FAI LURE TO PROVIDE ANY RELEASE DETECTION FOR UNDERGROUND PIPING ; FAILURE TO PERMANENTLY CLOSE OR UPGRADE A TEMPORARILY CLOS ED UST SYSTEM AFTER 12 MONTHS; AND FAILURE TO COMPLY WITH FI NANCIAL RESPONSIBILITY REQUIREMENTS