← EPA enforcement cases

PRASA & CAPR Vega Baja WWTP Northwest Trunk Sewer Pipeline Along State Rd PR #686

Administrative - Formal · FY2002 · — · Unilateral Administrative Order Without Adjudication · 87369

Penalty
Cost recovery
Compliance action

Case

Case Number
02-2002-3034
Type
Administrative - Formal
Lead
EPA
Outcome
Unilateral Administrative Order Without Adjudication
Multimedia
Self-disclosure
N

Defendants (1)

Summary

'PRASA/CAPR has violated the Clean Water Act by intermittently discharging sewage (wastewater) through a point source (a sewer pipeline) into Waters of the United States since at least March 4, 2000. In order to stop the discharge of sewage, PRASA/CAPR will have to finish the construction of a new trunk sewer pipeline -- with a larger diameter of the existing one -- that has been delayed on many times. The new trunk sewer pipeline would carry over the sewage to the Vega Baja Wastewater Treatment Plant for final treatment. PRASA/CAPR will have to finish the works by no later than 90 days of issuance of this ORDER.'

Source

Authoritative
EPA ECHO
Machine