← EPA Federal Register rules

Air Plan Approval; GA Infrastructure Requirements for the 2010 1-Hour NO2 NAAQS

air-emissions · Rule · Published 2016-09-14 · Effective 2016-10-14 · 81 FR 63106

Document

Document number
2016-21991
Federal Register citation
81 FR 63106
CFR reference
40 CFR 52
Type
Rule
Action
Final rule.
Category
air-emissions
Publication date
2016-09-14
Effective date
2016-10-14
EPA docket
EPA-R04-OAR-2015-0250

Abstract

The Environmental Protection Agency (EPA) is taking final action to approve portions of the State Implementation Plan (SIP) submission, submitted by the State of Georgia, through the Georgia Department of Natural Resources, Environmental Protection Division (GA EPD), on March 25, 2013, to demonstrate that the State meets the infrastructure requirements of the Clean Air Act (CAA or Act) for the 2010 1-hour nitrogen dioxide (NO<INF>2</INF>) national ambient air quality standard (NAAQS). The CAA requires that each state adopt and submit a SIP for the implementation, maintenance and enforcement of each NAAQS promulgated by EPA, which is commonly referred to as an "infrastructure" SIP. GA EPD certified that the Georgia SIP contains provisions that ensure the 2010 1-hour NO<INF>2</INF> NAAQS is implemented, enforced, and maintained in Georgia. EPA has determined that portions of Georgia's infrastructure submission, submitted on March 25, 2013, addresses certain required infrastructure elements for the 2010 1-hour NO<INF>2</INF> NAAQS.

Source

Authoritative
Federal Register document
Machine
JSON-LD · Markdown