Approval and Promulgation of Implementation Plans; Georgia; Nonattainment New Source Review Rules
other · Rule · Published 2008-12-30 · Effective 2009-01-29 · GA · 73 FR 79653
Document
Document number
E8-30813
Federal Register citation
73 FR 79653
CFR reference
40 CFR 52
Type
Rule
Action
Final rule.
Category
other
Publication date
2008-12-30
Effective date
2009-01-29
State
GA
EPA docket
EPA-R04-OAR-2006-0649-200750
Abstract
EPA is taking final action to disapprove a portion of a revision to the Georgia State Implementation Plan (SIP) submitted by the State of Georgia on March 5, 2007. The proposed revision was intended to modify Georgia's Nonattainment New Source Review (NNSR) permitting rules in the SIP to establish a new baseline emissions calculation procedure for the generation of emissions reduction credits to be used as offsets. EPA proposed to disapprove this revision on September 4, 2008; one comment letter, which supported EPA's proposed disapproval of the baseline emissions calculation, was received.