Effects of COVID-19 and the Events of January 6 Have Increased the Cannon House Office Building Renewal Project’s Contracts by $5.6 Million and Further Increases are Expected
Audit · Architect of the Capitol OIG · 2022-03-28 · about Architect of the Capitol
Report
Title
Effects of COVID-19 and the Events of January 6 Have Increased the Cannon House Office Building Renewal Project’s Contracts by $5.6 Million and Further Increases are Expected
Submitting OIG
Architect of the Capitol OIG
Component agency
Architect of the Capitol
Type
Audit
Publication date
2022-03-28
Summary
The objective of this audit was to determine theeffects of COVID-19 and the events of January 6, 2021, on the CHOBr Project.