Approval and Promulgation of Implementation Plans; Wisconsin
other · Rule · Published 2001-11-08 · Effective 2002-01-07 · WI · 66 FR 56447
Document
Document number
01-27829
Federal Register citation
66 FR 56447
CFR reference
40 CFR 52
Type
Rule
Action
Direct final rule.
Category
other
Publication date
2001-11-08
Effective date
2002-01-07
State
WI
EPA docket
WI107-01-7337a
Abstract
EPA is approving revisions to the minor source/minor modification pre-construction permitting requirements for Wisconsin Electric Power Company's (WE's) Pleasant Prairie Power Plant. The Pleasant Prairie Power Plant is located in Kenosha County at 8000 95th Street, Pleasant Prairie, Wisconsin. The Wisconsin Department of Natural Resources (WDNR) submitted the revised requirements on February 9, 2001, as amendments to its State Implementation Plan (SIP). The revisions include the expansion of the State's general construction permit exemption to include certain activities at the Pleasant Prairie facility.