Approval and Promulgation of Implementation Plans; Georgia Infrastructure Requirements for the 2008 Lead NAAQS
air-emissions · Rule · Published 2015-10-05 · Effective 2015-11-04 · GA · 80 FR 60045
Document
Document number
2015-24860
Federal Register citation
80 FR 60045
CFR reference
40 CFR 52
Type
Rule
Action
Final rule.
Category
air-emissions
Publication date
2015-10-05
Effective date
2015-11-04
State
GA
EPA docket
EPA-R04-OAR-2014-0442
Abstract
The Environmental Protection Agency (EPA) is taking final action to approve portions of the March 6, 2012, State Implementation Plan (SIP) submission, provided by the State of Georgia, through the Georgia Department of Natural Resources' Environmental Protection Division (EPD) for inclusion into the Georgia SIP. This final submission pertains to the Clean Air Act (CAA or the Act) infrastructure requirements for the 2008 Lead national ambient air quality standards (NAAQS). The CAA requires that each state adopt and submit a SIP for the implementation, maintenance, and enforcement of each NAAQS promulgated by EPA, which is commonly referred to as an "infrastructure" SIP. EPD certified that the Georgia SIP contains provisions that ensure the 2008 Lead NAAQS is implemented, enforced, and maintained in Georgia. With the exception of provisions pertaining to prevention of significant deterioration (PSD) permitting which EPA has already approved, EPA is taking final action to approve Georgia's infrastructure submission, provided to EPA on March 6, 2012, as satisfying the required infrastructure elements for the 2008 Lead NAAQS.